A number of mega projects are in pipeline for arrangement of foreign assistance or their execution. These mega projects are likely to be funded by multiple donors.

2.   For the purpose of projects oversight and donors coordination, it has been decided to establish focal points in the EAD for an integrated response and follow up. The following projects are assigned to the sections indicated against each:-

S.No.

Name of Projects

Focal Points in W&P

1

Pakistan Power Park Company PPHCL (Gaddani 2x660 MW on imported Coal (PC-II)

DS (NTDC)

2.

Neelum Jhelum Hydropower Projects

S. O. (Dev. Power)

3.

4500-MW, Diamer Basha Dam

S.O. (Dev. Water)

4.

4300 MW Dasu Hydro Power Projects

S. O. (Dev. Power)

5.

National Power Construction Company, Privatization

S. O. (Entities)

6.

Kishanganga Hydro power Projects /Ratle etc

S. O. (Water)

7.

Karkey

S. O. (PF)

8

Prime Minister’s Office letters

S.O. (C&C) 

9.

Court Cases

S. O. (Law)

10

CASA-1000 Constructions of Transmission Line from Aghanistan to Pakistan

S. O. (NTDC)

11.

JV Projects of GoS for Thar Coal Mining and Power

S. O. (GENCOs)

12.

2x660 MW Fired Power Projects at Jamshoro

S. O. (GENCOs)

13.

Conversion of 450 MW and 1 & 2 on coal from RFO at Jamshoro

S. O. (GENCOs)

14.

Conversion of 600 MW Unit 1-6 on Coal from RFO at Muzaffargarh

S. O. (GENCOs)

15.

Transmission Line for Power dispersal from Gandani

S. O. (NTDC)

 

3. In future all correspondence made by individual Sections relevant to these projects may be endorsed to focal points for their information and record.

 

4.   This issues with the approval of Secretary, Water and Power.

 

 

 

(Umar Farooq)